Provo Airport expansion update: Three gates expected to open in 2027, full completion slated for 2029
- Crews work on phase three of construction at the Provo Airport Friday, Nov. 20, 2026.
- People travel through the Provo Airport Friday, Nov. 20, 2026.
- Crews work on phase two of construction at the Provo Airport Friday, Nov. 20, 2026.
The Provo Airport is seeing constant growth, both in the number of passengers passing through its gates and the infrastructure being built to support them.
The transportation hub is on track for a record 1.25 million passengers in 2026, while phases two and three of a projected $160 million airport expansion are seeing visible progress.
The bustle occurs simultaneously. As passengers get dropped off and picked up at the terminal, construction crews immediately to the north are riding forklifts and building the new structure.
“It’s fun,” said Airport Director Brian Torgersen. “We kind of joke we’d like to be able to operate for at least 24 hours without something changing.”
The four-phase project that first started in 2025 is scheduled to be fully completed in 2029. It will expand the airport to 10 gates, transform the baggage and ticketing areas and pave the full airport parking lot.
Funding comes from various governmental entities, notably $78 million from Utah County’s TRCC funds, along with support from the FAA, state of Utah, Provo and Mountainland Association of Governments.
An estimated $130 million price tag set in 2025 has grown by $30 million, though, due to increasing material and labor costs, according to Torgersen. He said that has slightly pushed back phase four, expanding to the south side of the airport, which is currently in the design phase. The airport hopes to start phase four construction in spring 2028.
“We’re working with the city, the county, the state, and our federal legislators to identify additional funding to get us through phase four, which is coming online very well at this point,” Torgersen said.
Earlier phases are moving forward.
Phase one expanded the tarmac’s apron and is complete. Phase two, which includes ticket counter expansions, baggage handling, baggage screening and other equipmment and facilities, has had a tight timeline to take advantage of federal funding, Torgersen said. The first parts of the phase are anticipated to open in spring 2027.
Phase three, expanding the size of the terminal to the north, reached an important milestone last week with the placement of the final steel beam on the structure and was celebrated during a topping-out ceremony. The first three gates on the north expansion should be open before Thanksgiving 2027, according to Torgersen.
“And opening those three gates will allow us to remove some of the temporary facilities that, if you’ve flown in and out of the airport right now, you’ll see we’ve got some temporary holdroom space outside of the main terminal that’s allowing us to keep operations moving during construction,” Torgersen said.
He added that the airport is also under contract with a contractor to begin parking lot construction, with the goal of completing it by late summer or fall 2027.
The expansion is a massive undertaking that Torgersen said has required a huge effort in every phase of the project: funding, design, construction and operations.
He said extensive planning went into giving passengers a travel experience uninterrupted by construction. In the design phase, the airport spent hours coordinating how to keep the two areas separate while maintaining security and safety.
“It was a monumental task during the design process,” Torgersen said. “We like to tell people we spend as much time in the design process figuring out how to keep operations moving while being able to construct the expansion.”
Completing the airport expansion will allow PVU to accommodate additional routes, airlines and customers. The airport is not waiting to reach 10 gates before making a push for more traffic, though.
Torgersen said the airport reaches full capacity three times a day: early morning, midday and late at night. However, there is often space in the mid morning and late afternoon that can be filled.
“Even during construction, before we have those gates, we’re talking to new airlines and the ones that are here about filling in some of those gaps,” Torgersen said. “But then, the extra gates will give more opportunity for those more desirable departure times here out of Provo.”